  • Upcoming works

    Share Upcoming works on Facebook Share Upcoming works on Twitter Share Upcoming works on Linkedin Email Upcoming works link
    supporting image

    The Yamana Gold team and its partners will be carrying out various works in November and December.

    As usual, the crews are taking every possible measure to minimize disruptive impacts on the neighbourhood.

    Access road construction

    Construction of the access road to the site from chemin Aldermac is underway.

    Power line

    The dismantling of the 25KV power line on rang des Cavaliers should begin the week of November 2. Originally intended to serve the old Richmont project, the line was never used and will be repurposed for the Wasamac underground mining project.

    Increase in truck traffic near the Francoeur site

    We should be seeing a slight increase in truck traffic near the Francoeur site in December. We estimate some 10 trucks per hour, between 7:00 AM and 5:30 PM, using avenue Provencher from chemin Aldermac, in connection with construction of the access road to the planned industrial site. The company in charge of building the access road is Agrégat R-N.

    The Wasamac underground mining project team will provide regular updates to residents in the vicinity of the work and will be available at all times to answer any questions.

    By phone: 1 833 510-0330

    By SMS: 833-510-0330

    By email: wasamac@yamana.com

    At the community relations office: 14 rue d'Évain, Rouyn-Noranda, J0Z 1Y0

  • Potential Acquisition of Yamana Gold by Pan American Silver and Agnico Eagle Mines Ltd.

    Share Potential Acquisition of Yamana Gold by Pan American Silver and Agnico Eagle Mines Ltd. on Facebook Share Potential Acquisition of Yamana Gold by Pan American Silver and Agnico Eagle Mines Ltd. on Twitter Share Potential Acquisition of Yamana Gold by Pan American Silver and Agnico Eagle Mines Ltd. on Linkedin Email Potential Acquisition of Yamana Gold by Pan American Silver and Agnico Eagle Mines Ltd. link
    supporting image

    On November 8, 2022, Yamana Gold confirmed the activation of the arrangement agreement with Agnico Eagle Mines Ltd. (Agnico) and Pan American Silver, and at the same time announced the termination of the pending transaction with Gold Fields.

    Pursuant to the announcement, the shareholders’ vote scheduled to be held on November 21 has been cancelled and Yamana Gold will pay a termination fee of US$300 million to Gold Fields, in accordance with the terms of the arrangement agreement with that company.

    The board of directors of Yamana Gold has unanimously determined in good faith, after consultation with its outside financial and legal advisors, and upon the unanimous recommendation of the special committee of independent directors of the Board, that the Agnico - Pan American Transaction is a “Yamana Superior Proposal” in accordance with the terms of Gold Fields Arrangement Agreement. As a result, the Canadian Malartic Partnership and the Wasamac Underground Mining Project would be fully owned by Agnico Eagle.

    A copy of the press release issued on November 8, 2022 is available for viewing on the Company's website at http://www.yamana.com and under the Company's profile on SEDAR (www.sedar.com).

    The acquisition process will continue in the coming weeks. The Wasamac underground mining project team will be communicating regularly on this matter and remains available at all times to answer your questions.


    By phone: 1 833 510-0330

    By SMS: 833-510-0330

    By email: wasamac@yamana.com

    At the Community Relations Office, 14 rue d'Évain, Rouyn-Noranda, J0Z 1Y0

  • Planned work on Lac Hélène postponed to spring

    Share Planned work on Lac Hélène postponed to spring on Facebook Share Planned work on Lac Hélène postponed to spring on Twitter Share Planned work on Lac Hélène postponed to spring on Linkedin Email Planned work on Lac Hélène postponed to spring link


    The collection of samples aimed at characterizing the sediments planned for the end of February on Lac Hélène as part of the environmental impact study is postponed to springtime, after the melting of the ice on the lake.

    Adverse weather conditions did not allow the exercise to be carried out safely, so we decided to postpone it.

    As a reminder, the WSP team, the firm responsible for carrying out the environmental impact study, will review existing data on the lake's hydrology by taking surface water samples. They will also conduct a hydrological assessment to establish current conditions as well as predictive simulations to ascertain the potential impacts of the future mine on the lake's water level – a point raised by area residents. At this time, the potential impacts are estimated to be minimal.

    This exercise should not create a disturbance in the natural environment or for people living near the lake.

    Area residents will be notified once the new dates for the work are known.

    Should you have any questions regarding this work, please do not hesitate to contact us by phone at 1 833 510-0330 or via E-mail: wasamac@yamana.com


  • Sample Collection on Lac Hélène, February 28 to March 3

    Share Sample Collection on Lac Hélène, February 28 to March 3 on Facebook Share Sample Collection on Lac Hélène, February 28 to March 3 on Twitter Share Sample Collection on Lac Hélène, February 28 to March 3 on Linkedin Email Sample Collection on Lac Hélène, February 28 to March 3 link

    As part of the environmental impact assessment, samples aimed at analyzing lake sediments will be taken on Lac Hélène between February 28 and March 3.

    The work will involve taking a maximum of eight samples from four different stations – no more than two samples per station – using a vibracorer placed directly on the lake ice.

    Figure 1 shows the location of the proposed stations. In the event of a problem, such as inadequate ice conditions at a particular location, the station could be relocated nearby.



    Residents of the Évain sector told us that they observed a fluctuation in the water level of Lac Hélène in the past. The crew from WSP, which will carry out the work, will review existing data on the lake's hydrology by taking surface water samples. They will also conduct a hydrological assessment to establish current conditions as well as predictive simulations to ascertain the potential impacts of the future mine on the lake's water level – a point raised by area residents. At this time, the potential impacts are estimated to be minimal.

    This exercise should not create a disturbance in the natural environment or for people living near the lake. The work will take place during the day, supervised by our project superintendent. Access to the lake will be by snowmobile via public land on the north shore of the lake.

    Should you have any questions regarding this work, please do not hesitate to contact us by phone at 1 833 510-0330 or via E-mail: wasamac@yamana.com

  • Start of works planned on September 7th as part of the environmental impact study

    Share Start of works planned on September 7th as part of the environmental impact study on Facebook Share Start of works planned on September 7th as part of the environmental impact study on Twitter Share Start of works planned on September 7th as part of the environmental impact study on Linkedin Email Start of works planned on September 7th as part of the environmental impact study link

    The works announced in the notice of work mailed to neighbors in the area in mid-August, and available here will begin on September 7th. For now, we estimate that the works should be completed at the end of October. The works will take place on a 7/7 schedule, during the day.

    Several measures have been put in place to ensure that activities are carried out with respect for the neighborhood. We remind you that in the event of a problem, you can contact our team at the following coordinates:

    By phone or text: 1 833 510-0330

    By email at wasamac@yamana.com(External link)

    Online, using the form available in the «Exploration program» section of www.consultationswasamac.com

  • Notice of works – Environmental Impact Assessment – August and September 2021

    Share Notice of works – Environmental Impact Assessment – August and September 2021 on Facebook Share Notice of works – Environmental Impact Assessment – August and September 2021 on Twitter Share Notice of works – Environmental Impact Assessment – August and September 2021 on Linkedin Email Notice of works – Environmental Impact Assessment – August and September 2021 link
    supporting image

    As part of the environmental impact assessment to be done for the Wasamac underground mining project, various works will be carried out in the project area over a few weeks starting at the end of August. All details can be found here. The precise start date will be posted on this platform.

    Should you have any questions or comments, we invite you to contact us by phone or text at 1-833-510-0330, or by email at wasamac@yamana.com(External link).

  • April 9, 2021 - Notice: Helicopter geophysical surveys

    Share April 9, 2021 - Notice: Helicopter geophysical surveys on Facebook Share April 9, 2021 - Notice: Helicopter geophysical surveys on Twitter Share April 9, 2021 - Notice: Helicopter geophysical surveys on Linkedin Email April 9, 2021 - Notice: Helicopter geophysical surveys link
    supporting image

    As part of the exploration program to develop the Wasamac underground mining project, geophysical work will be done by helicopter in early April 2021 in the vicinity of the Wasamac mining property in Evain. A map of the area flyover area is available on the www.consultationswasamac.com platform.


    The survey work will be carried out by Novatem Airborne Geophysics. The average altitude will be 18 metres on unobstructed routes. Where dwellings are present, the helicopter will increase its altitude to 90 metres over the buildings and will fly at an average speed of 125 km/hr. The aircraft used by the company is equipped with the quietest technology. The work will take place over a period of approximately one week.


    We remind you that if you have any questions or comments about the Wasamac underground mining project, our contact details are as follows :


    Telephone: 819-763-1085

    Email: wasamac@yamana.com(External link)

    Our online platform: www.consultationswasamac.com

  • February 15, 2021 - Ambient noise measurements have begun on the exploration site

    Share February 15, 2021 - Ambient noise measurements have begun on the exploration site on Facebook Share February 15, 2021 - Ambient noise measurements have begun on the exploration site on Twitter Share February 15, 2021 - Ambient noise measurements have begun on the exploration site on Linkedin Email February 15, 2021 - Ambient noise measurements have begun on the exploration site link
    supporting image

    The specialized acoustics company hired by Yamana Gold has completed the installation of sound level meters at various locations in the preferred areas where exploration activities will begin in March 2021. These state-of-the-art instruments are used to measure the current ambient noise level as well as that of exploration work is in progress.

    It was important for our team to take sound measurements before exploration so that we could compare the results with those obtained when work commences. We are aware that in the past, the work (particularly the noise) may have created inconveniences for the neighborhood. The data we collect will allow us to adjust our practices and measures to minimize the impact of drill noise in the vicinity. Acoustic screens will also be installed at various locations to mitigate possible sound pollution.

    We look forward to neighbourhood collaboration from the moment the work begins to ensure monitoring and follow-up of the exploration work. We invite area residents to give us feedback so that we can make changes in response to reports we receive.

    If you have any questions or comments on noise monitoring and mitigation measures, or any other matter relating to the Wasamac underground mining project, please contact us at:

    By phone: 819-763-1085

    By email: wasamac@yamana.com